Below are Letters of Agreements (LOA’s), Memorandums of Understanding (MOU’s – which are essentially the same as LOA’s), and Review Committee decisions (RC’s) from the current and previous contract cycles.  For other documents and historical research, consult the ESC PG&E steward database or contact your Union Rep.

Use the search box to the right to filter for relevant documents.

Found 199 Results

MOU 18-03 EOT Design Centers

This bases EOT lists for Electric Estimators on the footprints of the Design Centers instead of the previous Local HQ’s. This agreement is important because it preserves the concept of Estimators at each headquarters working EOT within the footprint of that HQ.


MOU 18-02 Field Checking

Six-month pilot program in which Job Owners will collect basic information on every job and possibly more detailed information, depending on their qualifications. This means that Job Owners who were not previously Estimators will not be required to collect technical data, but will be encouraged to learn how to. It was important to make this agreement based on feedback from Job Owners about their workload and the impact of new additional fielding duties.


MOU 18-01 SPD GDPME Work Schedules

Preserves and expands options for starting times to promote work-life balance for SPD and Estimators and ADE’s in Gas Ops (“GDPM&E”).


LOA 18-08 2018 Two-year Contract Extension

Provides for extension of current contract provisions for two years, with 3% GWI in 2020 and 2021 each, and reopener bargaining for benefits when IBEW will also be negotiating employee benefits.


LOA 18-06 Gas Mapping Consolidation

Provides a 24-month period with incentives for Gas Mappers to move voluntarily into five central offices, 1 per Bid Region plus Bishop Ranch. Incentives are $20K in first year, $10K in second year, plus $5K moving allowance, if qualified. No layoffs or involuntary relocations (some exception) for the 24 months.


LOA 18-05-R1 Electric Mapping Consolidation

Provides a 24-month period with incentives for Electric Mappers to move voluntarily into four central offices plus DCC’s. Incentives during calendar year 2018 only are $20K for System Center or DCC, $10K for other offices, plus $5K moving allowance, if qualified. No layoffs or involuntary relocations (some exception) for the 24 months.


LOA 18-04 DCPP Retention Agreement

Cancels and supersedes previous retention agreement (LOA 16-18) in accordance with CPUC decision. Retention program 15% of base pay for seven years in two periods. Enhanced placement and other options.


LOA 18-02 Service Planning Re-org, New Business Rep, Permit Facilitator

Establishes the New Business Rep and Permit Facilitator classifications; Voluntary relocation incentive program for Estimators, ADE’s, SNBR’s, IPE’s and a few Gas Distribution Engineers; Prevent layoffs and most involuntary relocations for those classifications for two years; RDO’s for Estimators in Design Center locations; Some changes to work process between Estimating offices, and between SNBR and Gas DE


LOA 18-01 Sr Gas Distribution Engineers

Establishes job descriptions, salary range and other provisions for Senior and Senior Consulting Gas Distribution Engineers and includes revision to existing Gas Distribution Engineer job description.


PRC 726 Routine Estimator Upgrade to Supervisor

Clarifies issues around upgrades to supervisor. Routine level employees still in training should NOT be upgraded to Supervisor at all; if this somehow happens, after two weeks their training will be frozen and they will not be allowed to work OT.